The requirements of SOLAS Regulation II-3/3-13 will vary depending on the criteria below (see Figure1):

First criterion:

Keel laying date of ship:

on or after 1 January 2026

Installation date of anchor handling winch:

on or after 1 January 2026

Compliance date with Reg. II-1/3-13:

1 January 2026

Second criterion:

Keel laying date of ship:

before 1 January 2026

Delivery date of anchor handling winch:

on or after 1 January 2026

Compliance date with Reg. II-1/3-13:

1 January 2026

Anchor handling equipment which meets the first or second criterion must comply with the following requirements of SOLAS Regulation II-1/3-13:

A) Design, construction, installation (as per requirements of the vessel’s RO)
B) Thorough examination and test (as per MSC.1/Circ.1662)
C) Maintenance, operation, inspection and testing (as per MSC.1/Circ.1662)

Third criterion:

Keel laying date of ship:

before 1 January 2026

Installation date of anchor handling winch:

before 1 January 2026

Compliance date with Reg. II-1/3-13:

latest at first Renewal Survey of the ship after 1 January 2026

Anchor handling equipment which meets the third criterion must comply with the following requirements of SOLAS Regulation II-1/3-13:

B) Thorough examination and test (as per MSC.1/Circ.1662)
C) Maintenance, operation, inspection and testing (as per MSC.1/Circ.1662)

Figure 1: Overview of compliance dates for Newbuilding and Fleet in Service

 Figure 1: Overview of compliance dates for Newbuilding and Fleet in Service